Train 1 (Ore Train Eng Light) Main Yard to Sherrillville to Steelmill to Sherrillville to Main Yard
When train 1 is complete train 2 will be ready
Scheduled work at Main Yard
Scheduled work at Sherrillville
Scheduled work at Steel Mill
Scheduled work at Sherrillville
Scheduled work at Main Yard
Pick up – Round House
Pick up UP 3845 Caboose Orange Caboose Track
Scheduled work at Sherrillville
Pick up (10)Hopper Ore cars Ore Track
Scheduled work at Steel Mill
Pick up (10)Hopper Ore cars Steel Mill Siding
Set out (10)Hopper Ore cars Steel Mill Siding
Scheduled work at Sherrillville
Set out (10)Hopper Ore cars Ore Track
Scheduled work at Main Yard
Set out UP 3845 Caboose Orange Caboose Track
Set out – Round House
Train 2 Ore Switching at Steelmill
Move cars between Steelmill Siding and High LinesUse engine UP 1304 H10-44 and uncoupler buffer car
Scheduled work at Steel Mill
Move (3)Hopper Ore cars High Line Tk2 to Steel Mill Siding
Move (7)Hopper Ore cars High Line Tk1 to Steel Mill Siding
Move (3)Hopper Ore cars Steel Mill Siding to High Line Tk2
Move (7)Hopper Ore cars Steel Mill Siding to High Line Tk1